Project update June 2026
On 16 June 2026, following discussion with the Planning Inspectorate, Kingsway Solar Farm Limited has withdrawn its current Development Consent Order (DCO) Application for the Kingsway Solar Farm.
Kingsway Solar Farm Limited remains determined to deliver the best possible project which considers all the potential impacts as effectively as possible. We intend to work with the Planning Inspectorate and key stakeholders to understand and address key issues and information requirements, in order to bring forward the strongest possible proposals for this critical national project. The intention is to resubmit the DCO Application once these issues have been reviewed and appropriately addressed, and a timeline for that will be provided to all stakeholders as soon as possible.
Kingsway Solar Farm would have the capacity to generate around 500 megawatts (MW) of electricity and power approximately 175,000 homes annually, making a significant contribution towards increasing national energy security.
David Vernon, Head of NSIP Projects, from Kingsway Solar Farm Ltd, said:
“Kingsway Solar is a project designed to address national need for home grown, affordable, clean and reliable energy. We have been working extremely hard over the last few years to develop our proposals and bring forward a high quality scheme that meets those objectives while managing any impacts to the greatest degree possible.
We intend to re-engage with stakeholders and are committed to addressing any outstanding issues and strengthen our proposals. We look forward to working with local and national stakeholders in the coming weeks as we look to resubmit our DCO Application in due course.
I appreciate everyone’s patience and continued engagement as we go through this next phase.”
The Scheme
Kingsway Solar Farm Limited is developing proposals for a new solar farm and overhead line connection to the national grid between Burwell and Balsham in Cambridgeshire (the "Scheme").
The scheme would have capacity to generate around 500 megawatts (MW) of electricity, the equivalent of powering approximately 175,000 homes annually.
It would also include associated infrastructure, including co-located battery energy storage systems (BESS) and inter-array connections to link together the land parcels where the solar panels are located.
Our Vision and Objectives
Our vision for Kingsway Solar is to deliver cleaner, greener, and lower-cost energy, whilst delivering direct benefits to the local environment and community.
Generate renewable electricity to support the transition to net zero and the UK’s ambition to be increasingly self-sufficient in energy
Produce clean energy for the equivalent of approximately 175,000 homes
Deliver a Scheme that enhances local ecology and achieves Biodiversity Net Gain
Work with the local community to support community initiatives throughout the lifetime of the Scheme